What you will be able to do
- Explain merit-order dispatch, security-constrained economic dispatch and unit commitment, and identify where each is actually applied in the region
- Construct a day-ahead schedule and reserve allocation for a simplified system and defend the choices made
- Operate a simulated control room through defined contingencies — generator trip, tie-line trip, sudden renewable ramp — and account for the decisions taken
- Explain the operational obligations that flow across an interconnection and how a regulator verifies compliance with them
- Specify the data and audit trail a regulator should require from a system operator, and design the monitoring regime around it
Day by day
- 1Day 1 (online)
Foundations
generation cost structures and merit order; unit commitment and dispatch; reserves — primary, secondary, tertiary — and how they are sized; the regulator’s proper interest in operational decisions it does not take.
- 2Day 2 (simulator)
Scheduling
building a day-ahead schedule for a simplified national system; incorporating variable renewable forecast and forecast error; reserve procurement decisions.
- 3Day 3 (simulator)
Real-time operation and contingency
operating through a generator trip and a sudden renewable ramp; frequency response and load shedding decisions; post-event reconstruction from SCADA data.
- 4Day 4 (simulator)
Interconnected operation
two teams operate interconnected control areas; scheduled interchange, inadvertent flows and settlement; a tie-line trip and the coordination that follows; power pool rules and obligations.
- 5Day 5
Regulatory oversight and capstone
what a regulator should require, inspect and publish; participants draft a system operator performance monitoring and reporting framework, then reconstruct and account for one contingency event from the week’s simulator logs.
Cases and data
A simplified but realistic regional system model; SCADA event logs generated during the week’s own simulator sessions; an anonymised real interconnection operating agreement.
Tools
SCADA and power pooling simulation laboratory; dispatch and reserve scheduling worksheets; an event reconstruction template.
Your work product
The system operator monitoring framework and the contingency event reconstruction, jointly assessed by faculty and a serving system operator.
Faculty
A serving or recently serving system operations manager from a regional system operator or power pool, supported by a power systems engineer and the Programme and Training Manager.
Linked to peer review
Offered to regulators scoring low on cluster 5: Grid rules, governance & regional alignment.
How peer review works →Counts towards
Technical elective for the CCER; core course for the System and Network Operations endorsement
The CCER pathway →